Listing the Critical Path using Schedule Settings for all selected schedules and Baselines. Schedule: Harbour Pointe, Data Date = 01JUL07 Total Float of 0 hours is used to determine the critical activities listed below. Activity L2000, Landscape & Irrigation Activity M9000, Substantial Completion - All TCO Activity M2000, Complete Building 1 Baseline: Harbour Pointe - B1, Data Date = 08JAN07 Total Float of 0 hours is used to determine the critical activities listed below. Activity M0100, Building Pad Delivered by Owner Activity M0199, Permits Received - Start Site Work Activity RU2010, Site Electrical Work & Temp Power Activity ST2001, Building Pad Including UG Utils Activity RU2000, Storm Drainage Site Work Activity B1ST, Building 1 Structure Summary Activity C1S, Roads, Utilities & Pavers Summary Activity ST1030, Building Slab Incl. UG Utils Activity B2S, Building 2 Structure Summary Activity ST4010, Building Slab Incl. UG Utils Activity B3S, Building 3 Structure Summary Activity ST4020, First Floor Masonry Structure Activity ST3010, Building Slab Incl. UG Utils Activity B4S, Building 4 Structure Summary Activity ST4030, Second Floor Slab & Collar Beam Activity ST4040, Second Floor Masonry Structure Activity ST4050, Third Floor Slab & Collar Beam Activity ST3020, First Floor Masonry Structure Activity ST3030, Second Floor Slab & Collar Beam Activity ST4060, Third Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity ST3040, Second Floor Masonry Structure Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3060, Third Floor Masonry Structure Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3080, Fourth Floor Masonry Structure Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B2, Data Date = 04FEB07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST2001, Building Pad Including UG Utils Activity B1ST, Building 1 Structure Summary Activity ST1030, Building Slab Incl. UG Utils Activity B2S, Building 2 Structure Summary Activity ST4010, Building Slab Incl. UG Utils Activity B3S, Building 3 Structure Summary Activity ST4020, First Floor Masonry Structure Activity ST3010, Building Slab Incl. UG Utils Activity B4S, Building 4 Structure Summary Activity ST4030, Second Floor Slab & Collar Beam Activity ST4040, Second Floor Masonry Structure Activity ST4050, Third Floor Slab & Collar Beam Activity ST3020, First Floor Masonry Structure Activity ST3030, Second Floor Slab & Collar Beam Activity ST4060, Third Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity ST3040, Second Floor Masonry Structure Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3060, Third Floor Masonry Structure Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3080, Fourth Floor Masonry Structure Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B3, Data Date = 04MAR07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST1030, Building Slab Incl. UG Utils Activity B2S, Building 2 Structure Summary Activity ST4010, Building Slab Incl. UG Utils Activity B3S, Building 3 Structure Summary Activity ST4020, First Floor Masonry Structure Activity ST3010, Building Slab Incl. UG Utils Activity B4S, Building 4 Structure Summary Activity ST4030, Second Floor Slab & Collar Beam Activity ST4040, Second Floor Masonry Structure Activity ST4050, Third Floor Slab & Collar Beam Activity ST3020, First Floor Masonry Structure Activity ST3030, Second Floor Slab & Collar Beam Activity ST4060, Third Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity ST3040, Second Floor Masonry Structure Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3060, Third Floor Masonry Structure Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3080, Fourth Floor Masonry Structure Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B4, Data Date = 01APR07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST4010, Building Slab Incl. UG Utils Activity B3S, Building 3 Structure Summary Activity ST4020, First Floor Masonry Structure Activity ST3010, Building Slab Incl. UG Utils Activity B4S, Building 4 Structure Summary Activity ST4030, Second Floor Slab & Collar Beam Activity ST4040, Second Floor Masonry Structure Activity ST3020, First Floor Masonry Structure Activity ST4050, Third Floor Slab & Collar Beam Activity ST3030, Second Floor Slab & Collar Beam Activity ST4060, Third Floor Masonry Structure Activity ST3040, Second Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST3060, Third Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST3080, Fourth Floor Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity R4020, Place Mechanical Equipment Supports Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4030, Built-Up Asphalt Roofing Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity F4S100, Unit Finishes Building South - Floor 1 Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B5, Data Date = 06MAY07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST3020, First Floor Masonry Structure Activity ST4050, Third Floor Slab & Collar Beam Activity B3S, Building 3 Structure Summary Activity B4S, Building 4 Structure Summary Activity ST3030, Second Floor Slab & Collar Beam Activity ST4060, Third Floor Masonry Structure Activity ST3040, Second Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST3060, Third Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST3080, Fourth Floor Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity R4020, Place Mechanical Equipment Supports Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4030, Built-Up Asphalt Roofing Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity F4S100, Unit Finishes Building South - Floor 1 Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B6, Data Date = 03JUN07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST3040, Second Floor Masonry Structure Activity ST4070, Fourth Floor Slab & Collar Beam Activity B3S, Building 3 Structure Summary Activity B4S, Building 4 Structure Summary Activity ST3050, Third Floor Slab & Collar Beam Activity ST4080, Fourth Floor Masonry Structure Activity ST3060, Third Floor Masonry Structure Activity ST4090, Roof Slab Activity ST3070, Fourth Floor Slab & Collar Beam Activity ST4100, Stair and Elevator Masonry Structure Activity ST3080, Fourth Floor Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3090, Roof Slab Activity R4010, Place Roof Trusses and Sheathing Activity R4020, Place Mechanical Equipment Supports Activity B3R, Building 3 Roof Summary Activity ST3100, Stair and Elevator Masonry Structure Activity R4030, Built-Up Asphalt Roofing Activity R4040, Felt and Tile Roofing Activity ST3110, Roof Slab/Collar Beam Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity F4S100, Unit Finishes Building South - Floor 1 Activity B4IF, Building 4 Interior Finishes Summary Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO Baseline: Harbour Pointe - B7, Data Date = 01JUL07 Total Float of 0 hours is used to determine the critical activities listed below. Activity ST4090, Roof Slab Activity ST3070, Fourth Floor Slab & Collar Beam Activity B3S, Building 3 Structure Summary Activity B4S, Building 4 Structure Summary Activity ST3080, Fourth Floor Masonry Structure Activity ST4100, Stair and Elevator Masonry Structure Activity ST4110, Roof Slab/Collar Beam Activity ST3090, Roof Slab Activity ST3100, Stair and Elevator Masonry Structure Activity R4010, Place Roof Trusses and Sheathing Activity R4020, Place Mechanical Equipment Supports Activity B3R, Building 3 Roof Summary Activity ST3110, Roof Slab/Collar Beam Activity R4030, Built-Up Asphalt Roofing Activity R4040, Felt and Tile Roofing Activity R3010, Place Roof Trusses and Sheathing Activity R3020, Place Mechanical Equipment Supports Activity B4R, Building 4 Roof Summary Activity R3030, Built-Up Asphalt Roofing Activity R3040, Felt and Tile Roofing Activity F4N100, Unit Finishes Building North - Floor 1 Activity B3IF, Building 3 Interior Finishes Summary Activity F4S100, Unit Finishes Building South - Floor 1 Activity B4IF, Building 4 Interior Finishes Summary Activity F4N200, Unit Finishes Building North - Floor 2 Activity F3N100, Unit Finishes Building North - Floor 1 Activity F3S100, Unit Finishes Building South - Floor 1 Activity F3N200, Unit Finishes Building North - Floor 2 Activity F3S200, Unit Finishes Building South - Floor 2 Activity F3N300, Unit Finishes Building North - Floor 3 Activity F3S300, Unit Finishes Building South - Floor 3 Activity F3N400, Unit Finishes Building North - Floor 4 Activity F3S400, Unit Finishes Building South - Floor 4 Activity F39000, Final Inspections and Punchlist Activity M3000, Complete Building 4 Activity M9000, Substantial Completion - All TCO END OF REPORT ====================================================================